LitPol Link electricity interconnection, Alytus - Lazdijai, Lithuania

  • Building Type:
  • Energy Construction
  • Infrastructure
Fullscreen map Close

LitPol Link - the first electricity interconnection between Lithuania and Poland. It will connect the Baltic countries to the electricity infrastructure of Western Europe for the first time. LitPol Link will enable Lithuania, Latvia and Estonia to export and import electricity through Poland to Western Europe. Length is 51 km in territory of Lithuania.

HPM®, PPM® and PPM® special ECO galvanized bolts were used for structure-foundation connections.

Lithuania has relied on its Eastern neighbors for energy resources for many years, but this is coming to an end. The country’s first electric energy interconnection with Western Europe was put into operation from December 2015. Electricity is transmitted via a 163-km link with Poland, one of our closest allies throughout history.

Since the end of 2015 interconnection LitPol Link is a power bridge linking all three Baltic States with the West European power grid. This gives the three states access to a much larger and more diverse electricity market, which promotes competition and better prices. Everybody stands to win.

LitPol Link is not merely an energy transmission project. It is also an important partnership between two countries and regions. Mutual goals and joint projects will make Lithuania more secure and independent, both politically and economically.

Source: www.litpol-link.com

Read more down-arrow.png

Project facts

Developer:
AB Litgrid
Construction Company:
UAB Projektana
Delivery year:
2015
Completion year:
2015