Turbine Foundation Optimizer – For the Winds of the World |Pile Foundation

Pile Foundation – high performance on soft or semi-soft soil

The loads are transferred from the tower to the piles through the anchor cage and wide and shallow foundation.

Peikko optimizes and integrates the foundations and piles in the same design to lower the foundation size, weight, and costs. For example, a 5.5 MW turbine with a tower height of 120 meters uses:

  • 700 m3 of concrete (70 truckloads)
  • 90 t of steel (4 truckloads)
  • 1 Anchor cage (1 truckload)
  • Piles

 

-30%

 

CO2 emissions when compared to traditional solutions

Components

Installation phases

  1. 1-2 days
    Piling

  2. 1 day
    Anchor cage assembly

  3. 3-4 days
    Reinforcement

  4. 1 day
    Concreting

  5. 6-8 days
    Total

Specialist equipment

Installation team

8 skilled workers

 

See our other solutions

Gravity7 Wind Turbine Foundation – Optimizing the size, weight and costs

Used on a variety of geotechnical conditions: semi‑soft soil, load‑bearing soil, and solid rock. 

Read more

Rock Wind Turbine Foundation – hard‑to‑beat CO2 emissions and costs

When solid bedrock is on the surface or max 2 meters deep, rock foundation is an optimum choice.

Read more

Cage Rock Foundation – making the most of weak rock

Cage rock foundation excels in locations with weak bedrock. It’s an option also if bedrock is 2‑5 meters below the surface.

Read more